Field Activities   Non-interactive line graphic

Non-interactive spacer The San Joaquin River Restoration Program is beginning field investigations to support gathering data so future decisions can be based on the best information available.  Information about field activities will be posted below to help the public understand when, where, and why SJRRP staff are out in various locations within the Program area.

Click on the link below to see upcoming field activies being planned. This document will be updated periodically.

Field Activity Advisories
Date(s)
Noise Surveys for the Mendota Pool Bypass and Reach 2B Improvements Project December 28 and 29, 2011
Groundwater Monitoring Well Maintenance (replacing covers)

November 14 through December 17, weather permitting

Groundwater Monitoring Well Installations November 9 -19; November 29 - December 16, 2011
Reach 4B, Eastside, and Mariposa Bypasses Geotechnical Investigations - Standard and Cone Penetration Tests September 27 through November, 2011
Mendota Pool Bypass and Reach 2B Channel Improvements Project - Test Pit Surveys for Potential Borrow Materials September 12 - 22, 2011

Biological Resource Field Surveys for Small Mammals and Wildlife Habitat in Support of the Mendota Pool Bypass and Reach 2B Improvements Project

Sunday, July 17 through Friday, July 22, 2011 (may be rescheduled between July 10 and August 12 if unfavorable weather conditions arise)

Juvenile Fall-run Chinook Salmon Migration and Survival Study

April - July, 2011
Aerial Surveys From Friant Dam to the Merced River Confluence and Bypasses March 25 - April 8, 2011

Biological and Cultural Resource Field Surveys in Reach 2B

 

February 28 - March 31, 2011

Aerial Surveys near the Friant-Kern Canal and Madera Canal

January 10 - 31, 2011

Bathymetric Surveys in Portions of Reach 4 and the Eastside Bypass


January 17 - 21, 2011

California State Lands Commission Boundary Surveys

Reach 2b Maps

Reach 3 Maps

Reach 4B1 Maps

 

November 29, 2010 - June 30, 2011
Groundwater Seepage Monitoring Well Installation November 9, 2010 - March 31, 2011
August 23-27, 2010

Aerial Flights over the SJRRP Area

A Reclamation contractor will perform five aerial flights over the SJRRP Area in Spring and Summer 2010 to help monitor vegetation and extent of aquatic habitat during different Spring 2010 Interim Flow amounts. Aerial imagery will be collected by plane from an altitude of at least 9,000 feet.

Spring/Summer 2010

U.S. Geological Survey Sediment Sampling

USGS Staff will collect suspended sediment and bedload samples from five locations along the San Joaquin River to help track the movement of sand and gravel during Water Year 2010 Spring Interim Flows. Slated to occur eight times at each site from March to late May, the data will be collected at Highway 41, Highway 145, Gravelly Ford, Chowchilla Bifurcation and a site approximately three river miles downstream of Mendota Dam. Dependent upon flow conditions, samples will be acquired by wading across the river or from bridges, boats and/or a cable-way crossing. Sampling will be conducted from the public right-of-way or through advance coordination with landowners. The sampling will measure the amount of sediments moving through the water column and along the streambed. 

March through May, 2010

 

Bathymetric Surveys Initiated in Reach 1B

California Dept. of Water Resources crews will conduct bathymetric surveys of the San Joaquin River from Highway 99 to Gravelly Ford. Conducted by boat, the surveys utilize sophisticated sonar to map the contours of a river channel.  Surveyor monuments stationed at concrete canal abutments operated by Fresno Irrigation District will serve as control points. Up to two aluminum skiffs and two kayaks will be deployed for the surveys. Boats will be launched and retrieved from Camp Pashayan, Donnie Bridge, Skaggs Bridge and Gravelly Ford. No land access is planned for the boat crews unless necessary for staff safety. Use of launch facilities, control points, and ponds connected to the river channel have been coordinated with landowners

 

Beginning March 8, 2010, for up to four weeks

Soil Salinity Surveys in Reaches 2B, 3, and 4

 

 

Late February through early May 2010

Bathymetric Surveys in Reach 3 ( mapping the river bottom)

August 24 - October 30, 2009 (excluding August 31-September 11)

Installing Groundwater Monitoring Wells

July 13, 2009, through January 31, 2010
Field Investigations in preparation for water flow monitoring activities May 26 - June 5, 2009

Biological field surveys in certain areas of the Eastside Bypass

May 2009
Site visits for potential seepage well locations near the SJ River April 2009

 

 

 

 

Non-Interactive Line

Contact the San Joaquin River Restoration Program
December 15, 2011

 

© Copyright 2009. San Joaquin River Restoration Program. All Rights Reserved.