Last updated on 05/19/2026

Arroyo Canal Fish Screen and Sack Dam Fish Passage Projects

Projects Update

 A major milestone was reached for the projects when the first concrete was placed for the river bypass on May 13. A commemorative photo was taken, harkening back to the era of peak Reclamation construction.

Construction crews pose for a photo in front of a cement mixer to commemorate the first placement of concrete for the Arroyo Canal Fish Screen and Sack Dam Fish Passage Projects on May 13, 2026.
Construction crews pose for a photo commemorating the first placement of concrete for the Arroyo Canal Fish Screen and Sack Dam Fish Passage Projects on May 13, 2026.

A series of concrete placements will form the river bypass channel in order to reroute the San Joaquin River and allow for fish passage around the existing Sack Dam and Arroyo Canal inlet. Water users will no longer use the 80 year-old Sack Dam to create the river elevation needed to make water deliveries to the gravity-fed Arroyo Canal. Instead, a new headworks structure will be constructed to create the water elevation needed to continue supplying the canal while meeting in-stream flow requirements.

Concrete for the river bypass channel walls will be poured in sections throughout the month of May before construction efforts turn to construction of the fish ladder and headworks components.

A concrete pump with an extension arm is used to place concrete for the river bypass channel.
A concrete pump with an extension arm is used to place concrete for the river bypass channel.

Below is a short video showing the recent construction efforts.

A total of 490 piles will be driven on site to provide structural support for the river and fish bypass channels, with hundreds currently having concrete placed as part of the river bypass channel. The video below highlights the pile-driving action!

 

Excavation of the main fish passage and river channels started in January and was completed in March 2026. 

In November and December 2025, crews completed vegetation clearing the east bank of the project area, including installing sheet piling to protect the project site from San Joaquin River flows.

An excavator removes vegetation from the project site.
An excavator removes vegetation from the project site in advance of constructing the main project components.
A vibrating hammer drill rig is used to drive sheet piles into the riverbank in order to protect the project site from water.
A vibratory pile driver is used to install sheet piles along the riverbank in order to protect the project site from water.
An aerial view of cleared riverbank with heavy machinery and a wall of sheet piling encircling the project site.
The eastern bank of the project site with sheet piling installed. Sack Dam is in the foreground.
Construction crews drill test piles that will be used to support project components.
Construction crews drill test piles that will be used to support project components.

Project Overview

The Arroyo Canal Fish Screen and Sack Dam Fish Passage Project, like the Mendota Pool Bypass and Reach 2B Project, is integral to restoring spring-run Chinook salmon to the San Joaquin River. View a project fact sheet here!

This project implements two of the highest priority projects identified in the 2006 Settlement: fish passage around Sack Dam and a fish screen on the Arroyo Canal to prevent entrainment of juvenile Chinook salmon in the canal.

An artist rendering of the proposed Arroyo Canal Fish Screen and Sack Dam Fish Passage Project looking upstream.

This project is necessary in order to allow salmon to freely move up and down the river to complete their lifecycle (downriver to the ocean and upriver to spawn).

The project furthers the Department of the Interior’s efforts to restore Chinook salmon and other fish to the San Joaquin River and is authorized in the San Joaquin River Restoration Settlement Act (P.L. 111-11). Arroyo Canal and Sack Dam are owned and operated by Henry Miller Reclamation District #2131.

The dam and canal are the sole diversion and conveyance facilities for the reclamation district and provide agricultural water supply to approximately 47,000 acres of farmland in the San Joaquin Valley along with conveyance of water supply to Federal and State wildlife refuges and private duck clubs. The project was awarded in July 2025 and project construction started in November 2025. Project completion is expected in Summer 2028.

Key Project Components

An artist rendering of the proposed Arroyo Canal Fish Screen and Sack Dam Fish Passage Project looking upstream.

Project Media

Take a 360-degree tour of the completed project here!
Lorem ipsum dolor amet consec tetur adiris elit eiusmod temsor execur sante dolore.
See All Media
Arroyo Canal Fish Screen and Sack Dam Fish Passage Project Fact Sheet
Secret Link